project >> 2003: Calendar View doesn't show all tasks

by Ann » Sat, 06 Mar 2004 05:41:12 GMT

I don't have any filters applied, however when I do
Calendar View intermittant tasks are missing. When I
print a report I can see the tasks fine.

Does anyone have a resolution or can tell me what my ID10T
error might be?

Thanks,
Ann


Similar Threads

1. Calendar View doesn't show all tasks

2. how do I show summary tasks in calendar view of project 2003

Sorry, I'm new to project...I'm trying to inlclude the bolded task summary 
that I can view in the gantt chart, when in the calendar view. For some 
reason when I go to "options" while in the calendar view and try to select 
"show summary tasks" in the outline options section, it's not a highlighted 
box I can check. I can alter that box in the gantt view, though. Any hints?

3. completed milestone task doesn't show completed in timesheet view

4. Adding/Updating A Task's Custom Field View via SQL doesn't show up in MS Project

I'm trying to add/alter a task's custom field value  for field "Text5"
from a SQL.  Here is my test code:

DECLARE @TaskUID uniqueidentifier
DECLARE @ProjUID uniqueidentifier

SELECT @TaskUID = TASK_UID, @ProjUID = PROJ_UID FROM MSP_TASKS WHERE
Task_ID = 2060;

DECLARE @PropUID UniqueIdentifier
DECLARE @PropID int
DECLARE @PropType tinyint

SELECT @PropUID = MD_PROP_UID, @PropID = MD_PROP_ID, @PropType =
MD_PROP_TYPE_ENUM FROM MSP_PROJECT_CUSTOM_FIELDS WHERE MD_PROP_NAME =
'Text5';

SELECT @TaskUID, @ProjUID, @PropUID, @PropID, @PropType

DECLARE @FieldUID uniqueidentifier
SET @FieldUID = newid();

INSERT INTO MSP_TASK_CUSTOM_FIELD_VALUES
		(CUSTOM_FIELD_UID, PROJ_UID, TASK_UID, MD_PROP_UID,
MD_PROP_ID, FIELD_TYPE_ENUM, TEXT_VALUE, CREATED_REV_COUNTER,
MOD_REV_COUNTER)
	VALUES
		(@FieldUID, @ProjUID, @TaskUID, @PropUID, @PropID,
@PropType, 'Testing123',1,1)

SELECT * FROM MSP_TASK_CUSTOM_FIELD_VALUES WHERE TASK_UID = @TaskUID
and PROJ_UID = @ProjUID;

UPDATE MSP_PROJECTS SET PROJ_EXT_EDITED=1

When I execute this code, the database is properly updated but when I
open the project in MS Project Task 2060 doesn't have the updated
field value.  Can anyone see what I'm missing.

NOTE:  the same problem occurs if I try to change an existing custom
property.  Ie: replace the insert with:

UPDATE MSP_TASK_CUSTOM_FIELD_VALUES 
	SET TEXT_VALUE = 'Testing123'
	WHERE
		PROJ_UID = @ProjUID AND
		TASK_UID = @TaskUID AND
		MD_PROP_UID = @PropUID AND
		MD_PROP_ID = @PropID;

The database is updated correctly, but MS Project doesn't show the
change.  It does however, prompt me to save the "changes" when I
attempt to unload the project.

5. Applied Task Update Request View doesn't show all users

6. Project Server 2003 Tasks to show as Tasks - not Calendar entr

7. Project Server 2003 Tasks to show as Tasks - not Calendar entries

8. Showing Tasks and Sub-Tasks in the Calendar View

Hello,

I'm trying to use show both tasks and sub-tasks in the calendar view.  It 
seems like it only wants to show the sub-tasks but not the high-level one's.  
Basically I'm trying to display the same information found in the Gantt Chart 
but in a more traditional calendar view.  Is this possible?

Thanks,

Dan